Pa help po sa math please thankss!
Before, a project house can be built in 3 months by 20 men. Due to the COVID-19, a construction company downsized their workforce to 15 men to prevent more cost
1. Will they be able to lessen the time in building the house? Or, will it take longer time?
2. How long will it take to finish the house?
3. Suppose two workers got sick, how long the remaining workers finish construct the house?
Answers & Comments
Answer:
1:will longer time 2:Pa help po sa math please thankss!
Before, a project house can be built in 3 months by 20 men. Due to the COVID-19, a construction company downsized their workforce to 15 men to prevent more cost
1. Will they be able to lessen the time in building the house? Or, will it take longer time?
2. How long will it take to finish the house?
3. Suppose two workers got sick, how longthe remaining workers finish construct the house?
Step-by-step explanation:
ans:1:will longer time 2:20monts 3: 23 mons