In first sentence
M (men) = 20
W ( work/machine) = 5
D ( days) = 2
In second sentence
M' (men) = 8
D' ( days) = 2
W'(work done) = ?
[tex] \frac{M \times D}{W} = \frac{M' \times D'}{W'} \\ [/tex]
on putting the values on above formula,we get:
[tex] ⟹\frac{20 \times 2}{5} = \frac{8 \times 3}{x} \\ [/tex]
[tex]⟹ \frac{40}{5} = \frac{24}{x} \\ [/tex]
on cross multiplication,we get:
[tex]⟹40 \times x = 24 \times 5 \\⟹x = \frac{24 \times 5}{40} \\ ⟹x = 3machines[/tex]
Answer:
To solve this problem, we can use the concept of man-days, which represents the amount of work done by one person in one day.
20 men * 2 days = 40 man-days
Therefore, it takes 40 man-days to repair 5 machines.
Now, we can calculate the number of machines repaired by 8 men in three days.
Let's assume X represents the number of machines repaired.
8 men * 3 days = 24 man-days
Since the total man-days required to repair 5 machines is 40,
40 man-days / 5 machines = 24 man-days / X machines
40X = 5 * 24
40X = 120
X = 120 / 40
X = 3
Therefore, 8 men can repair 3 machines in three days.
[tex]........[/tex]
Copyright © 2024 EHUB.TIPS team's - All rights reserved.
Answers & Comments
اسلام علیکم !!
GIVEN:
In first sentence
M (men) = 20
W ( work/machine) = 5
D ( days) = 2
In second sentence
M' (men) = 8
D' ( days) = 2
TO FIND:
W'(work done) = ?
SOLUTION:
[tex] \frac{M \times D}{W} = \frac{M' \times D'}{W'} \\ [/tex]
on putting the values on above formula,we get:
[tex] ⟹\frac{20 \times 2}{5} = \frac{8 \times 3}{x} \\ [/tex]
[tex]⟹ \frac{40}{5} = \frac{24}{x} \\ [/tex]
on cross multiplication,we get:
[tex]⟹40 \times x = 24 \times 5 \\⟹x = \frac{24 \times 5}{40} \\ ⟹x = 3machines[/tex]
HENCE, 3 machines (W') are repaired by 8 men in 3 days.
Verified answer
Answer:
To solve this problem, we can use the concept of man-days, which represents the amount of work done by one person in one day.
Given that 20 men can repair 5 machines in two days, we can calculate the total man-days required to repair those machines as follows:
20 men * 2 days = 40 man-days
Therefore, it takes 40 man-days to repair 5 machines.
Now, we can calculate the number of machines repaired by 8 men in three days.
Let's assume X represents the number of machines repaired.
8 men * 3 days = 24 man-days
Since the total man-days required to repair 5 machines is 40,
we can set up a proportion to find the number of machines repaired by 8 men in three days:
40 man-days / 5 machines = 24 man-days / X machines
Cross-multiplying, we get:
40X = 5 * 24
40X = 120
Dividing both sides by 40:
X = 120 / 40
X = 3
Therefore, 8 men can repair 3 machines in three days.
[tex]........[/tex]