Questions


October 2023 1 22 Report
On February 1, 2024, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8.510,000. During 2024, costs of $2.170.000 were incurred with estimated costs of $4.170.000 yet to be incurred Billings of $2.570,000 were sent, and cash collected was $2.420.000 n 2025, costs incurred were $2.670.000 with remaining costs estimated to be $3,855,000 2025 billings were $2.920,000, and $2,645,000 cash was collected. The project was completed in 2026 after additional costs of $3.970.000 were incurred. The company's fiscal year-end is December 31 Arrow recognizes revenue over time according to percentage of completion. Required: 1. Calculate the amount of revenue and gross profit or loss to be recognized in each of the three years 2a. Prepare journal entries for 2024 to record the transactions described (credit "Cash, Materials, etc. for construction costs incurred). 2b. Prepare journal entries for 2025 to record the transactions described (credit "Cash, Materials, etc." for construction costs incurred). 3a, Prepare a partial balance sheet to show the presentation of the project as of December 31, 2024 3b. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2025​

Answers & Comments


Add an Answer


Please enter comments
Please enter your name.
Please enter the correct email address.
You must agree before submitting.

Helpful Social

Copyright © 2024 EHUB.TIPS team's - All rights reserved.