The number of days that a work can be finished varies inversely to the number of workers. A certain
project can be completed by 5 workers in 24 days. In order to finish the project sooner, the company plans to
hire additional workers. How many workers are needed to finish the project in 15 days?
"RESPECT PLSS"
Answers & Comments
Answer:
In order to finish the work in 15 days, 8 workers are needed
Step-by-step explanation:
5 workers can finish the job in 24 days
Which means 1 worker can finish the job in 120 days
24 × 5 = 120
If the job needs to be finished in 15 days, 8 workers is needed