Answer:
18 workers
Step-by-step explanation:
W = no. of work
R= no. of workers
t = no. of working days
W= R x T
W= (12 workers) (15 days)
W= 180
W=R x T where 180 then
180 = (R) (10 days)
(180÷10) = R
= 18 wokers :))