Answer:
A can complete the work in 10 days
B can complete the work in 15 days
Total work = LCM of time taken
Efficiency = Total work/Total time
LCM of (10, 15) = 30
Let the total work be 30 units
According to the question:
The amount of work completed by B in 5 days,
⇒ 2 × 5 = 10 units
Remaining work after 5 days,
⇒ 30 – 10 = 20 units
Now A and B work together
Then the total efficiency of A and B,
⇒ 3 + 2 = 5 units/days
Time taken to complete the work when A and B working together,
⇒ 20/5 = 4 days
The time taken to complete the work
⇒ 5 + 4 = 9 days
LCM of (10, 12, 15) = 60 units
→ The efficiency of A = 6 units
The efficiency of B = 5 units
→ The efficiency of C = 4 units
First 2 days (A + B + C) = (6+5+4)* 2 => 30units
Last 4 days work done by B alone =
5 x 420 units
Remaining Work = 60 - (30+20) - 10 units
The remaining work is completed by B and C = 10/(5+4) → 10/9 days
So total number of days = 2 + 4 + 10/964/9 days
.. Work was finished in 64/9 days
hope this helps ❤️
Copyright © 2024 EHUB.TIPS team's - All rights reserved.
Answers & Comments
Answer:
Given:
A can complete the work in 10 days
B can complete the work in 15 days
Concept used:
Total work = LCM of time taken
Efficiency = Total work/Total time
Calculation:
LCM of (10, 15) = 30
Let the total work be 30 units
According to the question:
The amount of work completed by B in 5 days,
⇒ 2 × 5 = 10 units
Remaining work after 5 days,
⇒ 30 – 10 = 20 units
Now A and B work together
Then the total efficiency of A and B,
⇒ 3 + 2 = 5 units/days
Time taken to complete the work when A and B working together,
⇒ 20/5 = 4 days
The time taken to complete the work
⇒ 5 + 4 = 9 days
∴ The total time take to complete the work is 9 days
Answer:
LCM of (10, 12, 15) = 60 units
→ The efficiency of A = 6 units
The efficiency of B = 5 units
→ The efficiency of C = 4 units
First 2 days (A + B + C) = (6+5+4)* 2 => 30units
Last 4 days work done by B alone =
5 x 420 units
Remaining Work = 60 - (30+20) - 10 units
The remaining work is completed by B and C = 10/(5+4) → 10/9 days
So total number of days = 2 + 4 + 10/964/9 days
.. Work was finished in 64/9 days
hope this helps ❤️