B. Give what is asked. (2 points each)
1. ________is needed to compare quantities and use formula.
2. The _________and floor finishing of cement concrete or stone or marble or mosaic etc. are usually taken as one job or one item.
3. __________are taken separately in cubic meter foe their net volume and quantities are calculated
4. __________terracing may also be calculated in cubic meter with average thickness.
5. _________usually, 12mm thick is calculated in square meter.
Please answer my questions ❤
Nonsense Report
Answers & Comments
Answer:
1)
2)base line concrete
3)supporting structure
4)lime concrete
5)plastering
sana makatulong