A train starts from rest from one station. The train is accelerated, it acquires a maximum velocity and travels some distance with this velocity. As the train approaches the next station, its motion is slowed down and finally the train comes to rest at the next station. Draw velocity-time graph for the motion. How can you find total distance.
Answers & Comments
Answer:
The graph would be a trapezium. The area under graph gives the distance travelled by the train.
Step-by-step explanation:
Hope you like it