Answer:
Step-by-step explanation:
A takes 9 days more than B to do a certain piece of work. Together they can do the work
in 6 days. How many days will A alone take to do the work ?
Let's denote the time B takes to do the work as
�
B days. According to the given information:
A takes 9 days more than
B to do the work, so the time
A takes is
+
9
B+9 days.
Together, they can do the work in 6 days.
The combined rate of
A and
B is the sum of their individual rates. The rate is inversely proportional to the time taken. So, if
A takes
A days to complete the work, then the rate of
A is
1
A
and the rate of
B is
B
.
The combined rate is then
, and it's given that together they can complete the work in 6 days. Therefore, we can write the equation:
=
6
Now, we know that
A=B+9. We can substitute this into the equation:
B+9
To solve this equation and find the values of
B, you can multiply through by the common denominator and then solve for
B. Once you find
B, you can then find
A since
A=B+9.
Please note that the solution involves algebraic manipulation, and the final answer will provide the number of days
A alone takes to do the work.
Let's denote the amount of work that A can do in one day as `1/A` and the amount of work that B can do in one day as `1/B`.
According to the problem, A takes 9 days more than B to do the work, so we can write this as `A = B + 9`.
Also, A and B together can do the work in 6 days, which means `(1/A) + (1/B) = 1/6`.
Substituting `A = B + 9` into the second equation, we get `(1/(B+9)) + (1/B) = 1/6`.
Solving this equation for B, we get `B = 7.5`.
Substituting `B = 7.5` into `A = B + 9`, we get `A = 16.5`.
So, A alone will take 16.5 days to do the work.
Copyright © 2024 EHUB.TIPS team's - All rights reserved.
Answers & Comments
Answer:
Step-by-step explanation:
A takes 9 days more than B to do a certain piece of work. Together they can do the work
in 6 days. How many days will A alone take to do the work ?
Let's denote the time B takes to do the work as
�
B days. According to the given information:
�
A takes 9 days more than
�
B to do the work, so the time
�
A takes is
�
+
9
B+9 days.
Together, they can do the work in 6 days.
The combined rate of
�
A and
�
B is the sum of their individual rates. The rate is inversely proportional to the time taken. So, if
�
A takes
�
A days to complete the work, then the rate of
�
A is
1
�
A
1
and the rate of
�
B is
1
�
B
1
.
The combined rate is then
1
�
+
1
�
A
1
+
B
1
, and it's given that together they can complete the work in 6 days. Therefore, we can write the equation:
1
�
+
1
�
=
1
6
A
1
+
B
1
=
6
1
Now, we know that
�
=
�
+
9
A=B+9. We can substitute this into the equation:
1
�
+
9
+
1
�
=
1
6
B+9
1
+
B
1
=
6
1
To solve this equation and find the values of
�
A and
�
B, you can multiply through by the common denominator and then solve for
�
B. Once you find
�
B, you can then find
�
A since
�
=
�
+
9
A=B+9.
Please note that the solution involves algebraic manipulation, and the final answer will provide the number of days
�
A alone takes to do the work.
Let's denote the amount of work that A can do in one day as `1/A` and the amount of work that B can do in one day as `1/B`.
According to the problem, A takes 9 days more than B to do the work, so we can write this as `A = B + 9`.
Also, A and B together can do the work in 6 days, which means `(1/A) + (1/B) = 1/6`.
Substituting `A = B + 9` into the second equation, we get `(1/(B+9)) + (1/B) = 1/6`.
Solving this equation for B, we get `B = 7.5`.
Substituting `B = 7.5` into `A = B + 9`, we get `A = 16.5`.
So, A alone will take 16.5 days to do the work.