A contractor undertakes to dig a canal 12 km long in 30 days with 80 men. After 10 days he found that only 3 km of canal is completed. How many men must now be employed to finish the work on time?

GIVE ONLY RELEVANT ANSWERS WITH FULL EXPLANATION...