Answer:
Sita working 8 hours a day does the job in 6 days
So working 4 hours a day will take 12 days
So Sita in 1 day does 1/12 of the work in 4 hours
Similarly in 1 day Gita does 1/9 of the work in 4 hours
So together in 1 day they do 1/12+1/9 = 21/108 = 7/36 of the work
So they will finish the job in 36/7 days OR 5.14 days ANSWER