To finish a job in 4 days required 14 workers
to finish the job in 1 day will require 14 *4 workers
in 3 days will require
(14 *4)/3
= 18 2/3 days
Copyright © 2024 EHUB.TIPS team's - All rights reserved.
Answers & Comments
Verified answer
Where:w = the number of work
r = the number of workers
t = the number of working days
SOLUTION:
W = R x T
W = (14 workers)(4 days)
W = 56
Since, w = r x t, where w = 56, then,
56 = (r) (3 days)
or
Verified answer
To finish a job in 4 days required 14 workers
to finish the job in 1 day will require 14 *4 workers
in 3 days will require
(14 *4)/3
= 18 2/3 days